Assembly Line Balancing
4.16 The letters in the table below represent work elements in an assembly precedence diagram.
(a) Construct the precedence diagram and (b) determine the total work content time.
(c) Use the largest candidate rule to assign work elements to stations using a service time
(T) of 1.5 min, and (d) compute the balance delay for your solution.
Work element or tasks A
B C
D
F
G
H
Time (min)
0.5 0.3 0.8
1.1
0.6
0.2
0.7 1.0 0.9 0.4
Preceding
A
A
A
B.C
D
B
F F G,H,I
4.17 Solve the previous problem but use the Kilbridge and Wester method in part (c).
4.18 Solve the previous problem but use the ranked positional weights method in part (c).
4.19 The table below defines the precedence relationships and element times for a new assem-
bled product. (a) Construct the precedence diagram for this job. (b) If the ideal cycle time
is 1.1 min and the repositioning time is 0.1 min, what is the theoretical minimum number
of workstations required to minimize the balance delay under the assumption that there
will be one worker per station? (c) Using the largest candidate rule, assign work elements
to stations. (d) Compute the balance delay for your solution.
Work Element
Immediate Predecessors
7. (min)
1
0.5
2
0.3
3
0.8
4
0.2
5
0.1
0.6
3
10.4
4,5
05
3,5
03
7,8
0.6
6,9
10