categoryهندسة صناعية وإنتاج schoolبكالوريوس event_available2026-07-14

السؤال

Transcribed Image Text:

Question 2: If the daily production rate for a crew that works in an activity is 400 units/day and the total crew cost per day is $1800. The material needed for daily work is 6.5 units at S 100/unit. a. Calculate the time and cost it takes the crew to finish 1600 units b. Calculate the total unit cost. Consider an eight-hour work day. Ans.

check_circle الجواب — حل مفصل خطوة بخطوة

hourglass_top