Problem 6-19
The following tasks are to be performed on an assembly line:
TASK SECONDS
TASKS THAT
MUST PRECEDE
A
30
B
16
A
21
B
15
B
17
C
14
D
20
E, F
H
9
G
The workday is 8 hours long. Demand for completed product is 900 per day.
a. Find the cycle time required to meet the desired output rate. (Round your answer to 1 decimal place.)
Cycle time
seconds per unit
b. What is the theoretical number of workstations required to meet the desired output rate? (Round up your answer to the next whole number.)
Number of workstations
d. Balance the line using the longest-operating-time rule. (Leave no cells blank - be certain to enter "0" wherever required. Round your answers to 1 decimal
place.)
Work Station
Task
Idle Time
(Click to select) ▼
(Click to select)
III
(Click to select) ▼
IV
(Click to select) ▼
V
(Click to select)
e. What is the efficiency of the line balanced as in part (d) assuming it is running at the cycle time determined in part
(a)? (Round your answer to 1 decimal place.)
Efficiency
%
f. Suppose that demand rose from 900 to 1,000 units per day. What would you do? (Round your answer for cycle
time down to the nearest whole number.)
(Click to select) cycle time to
seconds, which may require rebalancing the line.
g. Suppose that demand rose from 900 to 1,400 units per day. What would you do? (Round your answer for cycle
time down to the nearest whole number.)
(Click to select) cycle time to
seconds, which may require rebalancing the line.