تم الحل ✓
categoryإدارة مشاريع
schoolبكالوريوس
event_available2026-07-14
السؤال
Transcribed Image Text:
Problem 2: (10 Points)
Given the following network and activity time estimates:
5
79,20
1
9
6,10,15
6
3,20,35
4.12.15
2
Start
2.7.16
3
4,8,11
4
3,10,15
11
Finish
2.9,14
7
3,6,9,
8
5,9,16
10
4,12,16
(a) Determine the expected time and variance for each activity by drawing the table with the
format on Page 14 on Chapter 8 Notes.
(b) Which path is the critical path?
(c) Calculate the expected project completion time.
(d) Calculate the project variance.
9
13
Probabilistic Activity Times Example
Equipment
installation
6.8.10
Equipment testing
and modification
24.12
8
37.11ning
debugging
10
1.4.7
System
development
Manual
g
2
5
9
11
Finish
Start
3,6,9
2.3.4
2,4,8
.10,13
System
sing
System
changeover
Poton
recruiting
6
3.4.5,
Job
training
1.3.5
2221
Orientation
Time Estimates (weeks)
Time
Mean Variance
Activity
a
m
b
1
V
I
6
8
10
8
4/9
2
3
6
9
6
1
3
1
3
5
3
4/9
4
2
4
12
5
25/9
5
2
4
3
1/9
6
3
5
4
1/9
2
2
2
0
3
9
6
10
7
11
=
10
13
1442
16/9
4/9
I
9
4
Open With
Drint
14
check_circle الجواب — حل مفصل خطوة بخطوة
hourglass_top
🔒
الحل الكامل متاح للمشتركين
اشترك في أرشيف الأسئلة لعرض هذا الحل وآلاف الحلول المفصلة خطوة بخطوة من معلمين معتمدين.