Transcribed Image Text:
2. The continuous timing method in direct time study was used to obtain the element
times for a worker-machine task as indicated in the table below. Element c is a
machine-controlled element and the time is constant. Elements a, b, d, e, and fare
operator-controlled and external to the machine cycle, and were performance rated
at 80%. If the machine allowance is 25%, and the worker allowance for personal
time, fatigue, and delays is 15%, determine (a) the normal time and (b) standard time
for the cycle. (c) If the worker completed 360 work units working 7.2 hours on an 8-
hour shift, what was the worker's efficiency?
Element
Observed time (min)
a
b
с
d
e
f
0.18
0.30
0.88
1.12
1.55
1.80