categoryهندسة نفط وغاز schoolبكالوريوس event_available2026-07-13

السؤال

Transcribed Image Text:

Construct IPR of a well in a saturated oil reservoir using both Vogel's equation and Fetkovich's equation. The following data are given: Reservoir pressure: 3,500psia Tested flowing bottom-hole pressure, P: 2,500psia Tested production rate at pw, q: 600stb/day Tested flowing bottom-hole pressure, Pw2:1,500psia Tested production rate at pw/2, 92: 900stb/day

check_circle الجواب — حل مفصل خطوة بخطوة