2. Bridge City Developers is coordinating the construction of an office complex. As part of the planning process, the company generated the following activity list. Draw a project network that can be used to assist in the scheduling of the project activities. J Activity A B C D E F GHI Immediate Predecessor A, B A, B DECC F, G, H, I