تم الحل ✓
categoryإدارة مشاريع
schoolبكالوريوس
event_available2026-07-13
السؤال
Transcribed Image Text:
Activity
Activity Description
No
Duration
(months)
Predecessors
Detailed site investigation and survey
2
-
Detailed planning
ABCDEFGHIK
Н
LMNPORSTO
Q
Detailed design
Preparation of site
Relocate services
Re-align overhead track electrification
Access road and ramp construction
Piling
Construct foundations and abutments
Construct temporary supports to support bridge deck during
construction
Fabrication planning of structural steel components
Manufacture structural steel components (off-site)
Transport structural steel components and erect on-site
Erect pylons and fill with concrete
Construct main span deck on pre-cast concrete beams
Install stay-cables and lift the bridge deck off temporary supports
Remove temporary supports
Electrical system installation
U
Roadway surfacing (paving)
V Finishing and ancillaries
Commissioning-cut-over
Formal hand-over & ceremony
W
X
Y
Project sign-off
Z
AA
Project End
Administrative closure
256434123
2221231
TABCC DCH
F,G
C
L
M
J
H, K, N, P
R
3
1
1
S
2
S
2
T, U
1
V
W
X
W
0 (milestone)
Y, Z
Activity No
Activity Description
Resources
A
Detailed site investigation and survey
B
Detailed planning
C
Detailed design
Ꭰ
E
Preparation of site
Relocate services
F
Re-align overhead track electrification
Surveyors, Engineering, Project Manager
Project Manager, Engineering, Construction, Contractors
Engineering
Construction
Engineering
Engineering, Contractors
G
Access road and ramp construction
Construction
H
Piling
Construction, Contractors
J
Construct foundations and abutments
Engineering, Construction
K
Construct temporary supports to support bridge deck during construction
Engineering, Construction
L
Fabrication planning of structural steel components
Engineering, Manufacturer
M
Manufacture structural steel components (off-site)
N
Transport structural steel components and erect on-site
Engineering, Manufacturer
Transporter, Engineering
P
Erect pylons and fill with concrete
Construction, Engineering
Q
Construct main span deck on pre-cast concrete beams
Construction, Engineering
R
Install stay-cables and lift the bridge deck off temporary supports
Construction, Engineering
S
Remove temporary supports
Construction, Engineering
T
Electrical system installation
U
Roadway surfacing (paving)
V
W
X
Y
Z
Finishing and ancillaries
Commissioning-cut-over
Formal hand-over & ceremony
Project sign-off
Administrative closure
Construction, Engineering
Contractor, Engineering
Contractors, Engineering
Project Manager, Engineering, Construction, Contractors
Project Manager, Engineering, Construction, Contractors
AA
Project End
Project Manager, Engineering
Engineering
Project Manager
check_circle الجواب — حل مفصل خطوة بخطوة
hourglass_top
🔒
الحل الكامل متاح للمشتركين
اشترك في أرشيف الأسئلة لعرض هذا الحل وآلاف الحلول المفصلة خطوة بخطوة من معلمين معتمدين.