السؤال
Transcribed Image Text:
Lifang Wu owns an automated machine shop that makes precision auto parts. He has just compiled an input-output report for the grinding work center.
Period
Planned input
2
1
3
4
Total
85
85
105
105
Actual input
90
90
90
90
Deviation
Planned output
95
95
95
Actual output
85
85
80
95
80
Deviation
Initial backlog: 40
For the given information related to "inputs," the values for deviation and total are:
The deviation in period 2 =
The deviation in period 4= |
The total for "planned inputs"
The total for "actual inputs" =
The total deviation for "inputs" =
units (enter your response as an integer, including a minus sign if necessary).
units (enter your response as an integer, including a minus sign if necessary).
|
units (enter your response as an integer, including a minus sign if necessary).
units (enter your response as an integer, including a minus sign if necessary).
units (enter your response as an integer, including a minus sign if necessary).
For the given information related to "outputs," the values for deviation and total are:
The deviation in period 1 =
The deviation in period 3 =
The total for "planned outputs"
The total for "actual outputs"
The total deviation for "outputs"
units (enter your response as an integer, including a minus sign if necessary).
units (enter your response as an integer, including a minus sign if necessary).
units (enter your response as an integer, including a minus sign if necessary).
units (enter your response as an integer, including a minus sign if necessary).
units (enter your response as an integer, including a minus sign if necessary).
Fill in the cumulative values for the backlog in each of the periods (given an initial backlog of 40):
Period
Initial backlog: 40
1
2
3
4
Total