Questions 8: Consider the following information about a small project:
Task
Budget
Duration
(days)
Immediate
Predecessors
Shortest
Time
Acceleration
Cost per day
Possible
A
$200
2
None
2
B
$500
5
A
3
$30
с
$200
2
B
1
$15
D
$400
4
A
4
E
$300
B&D
1
$20
F
$400
E&C
2
$40
3
4
a. Identify the critical path by forward and backward paths. For the tasks that are not on
the critical path, identify their slacks.
b. At the end of 8th day, assume the following progress of the project:
a. Tasks A, B, D are 100% completed, and the actual costs spent for them are $200,
$500 and $450, respectively.
b. Task C is 80% completed, and already cost $100
c. Task E is 66.67% completed, and already cost $100
d. Task F is not started yet, and didn't cost anything either.
Evaluate the progress of the project by filling the following blanks (both in the table and
in the sentence below the table):
Task
Budget
Scheduled
Performed ACWP
BCWS
BCWP
Progress
Progress
A
$200
100%
100%
$200
B
$500
100%
100%
$500
с
$200
80%
$100
D
$400
100%
$450
E
$300
66.67%
$100
F
$400
0%
Total
The whole project is
("ahead of" / "behind”) schedule, and
("above" /
"under") budget.
c. Find the cost-effective way to reduce the completion time to 9 days.
Note: When you need to accelerate multiple tasks at the same time, please identify them in
a single step, such as: "Step **: Accelerate task(s)** and *
by
Step 1: Accelerate task(s).
by.
days
Step 2: Accelerate task(s).
by
days
Step 3: Accelerate task(s).
by
days
Step 4: Accelerate task(s).
by.
days
Step 5: Accelerate task(s),
by
days
days.
check_circle الجواب — حل مفصل خطوة بخطوة
hourglass_top
🔒
الحل الكامل متاح للمشتركين
اشترك في أرشيف الأسئلة لعرض هذا الحل وآلاف الحلول المفصلة خطوة بخطوة من معلمين معتمدين.