Questions 8: Consider the following information about a small project: Task Budget Duration (days) Immediate Predecessors Shortest Time Acceleration Cost per day Possible A $200 2 None 2 B $500 5 A 3 $30 с $200 2 B 1 $15 D $400 4 A 4 E $300 B&D 1 $20 F $400 E&C 2 $40 3 4 a. Identify the critical path by forward and backward paths. For the tasks that are not on the critical path, identify their slacks. b. At the end of 8th day, assume the following progress of the project: a. Tasks A, B, D are 100% completed, and the actual costs spent for them are $200, $500 and $450, respectively. b. Task C is 80% completed, and already cost $100 c. Task E is 66.67% completed, and already cost $100 d. Task F is not started yet, and didn't cost anything either. Evaluate the progress of the project by filling the following blanks (both in the table and in the sentence below the table): Task Budget Scheduled Performed ACWP BCWS BCWP Progress Progress A $200 100% 100% $200 B $500 100% 100% $500 с $200 80% $100 D $400 100% $450 E $300 66.67% $100 F $400 0% Total The whole project is ("ahead of" / "behind”) schedule, and ("above" / "under") budget. c. Find the cost-effective way to reduce the completion time to 9 days. Note: When you need to accelerate multiple tasks at the same time, please identify them in a single step, such as: "Step **: Accelerate task(s)** and * by Step 1: Accelerate task(s). by. days Step 2: Accelerate task(s). by days Step 3: Accelerate task(s). by days Step 4: Accelerate task(s). by. days Step 5: Accelerate task(s), by days days.

check_circle الجواب — حل مفصل خطوة بخطوة

hourglass_top