The MRP gross requirements for Item A are shown here for the next 10 weeks. Lead time for A is three weeks
and setup cost is $10. There is a carrying cost of $0.010 per unit per week. Beginning inventory is 92 units.
1
2
3
4
WEEK
5
6
7
8
9
10
Gross requirements
35
40
17
25
25
75
85
20
60
200
87
Use the least total cost and the least unit cost lot-sizing methods to determine the quantity to order with the first
order released with each method and which periods' requirements will be covered by that order.
Periods Covered
Quantity Ordered
13.05
4 to 7
Least total cost
25.45
4 to 9
Least unit cost