Problem 21-20
The MRP gross requirements for Item A are shown here for the next 10 weeks. Lead time for A is three
weeks and setup cost is $9. There is a carrying cost of $0.010 per unit per week. Beginning inventory is
75 units.
WEEK
1
2
3
4
5
6
7
8
9
10
Gross requirements 30
35
10
25
75
85
20
65
220
55
Use the least total cost and the least unit cost lot-sizing method to determine what quantity the first order
should be released and for which period.
Quantity Ordered
Period
Least total cost
180
4 to 8
Least unit cost
100
4 to 8