السؤال

Transcribed Image Text:

Consider the product structure diagram given in figure below. D (2) B (2) 2 weeks E (3) 2 weeks 1 week Product A Suppose that the master production schedule for product A is; F(2) 2 weeks Week 7 Demand 100 8 9 10 11 12 13 125 90 300 46 81 15 C (3) 1 week The holding cost for each item is $0,8 per part, per week and the fixed order cost is estimated to be $200. There is no scheduled receipts or on hand inventory for product B and F. a) Determine the planned order releases for components B, and F using Least Unit Cost heuristic. b) Determine the lot sizes using the Silver-Meal heuristic. I