تم الحل ✓
categoryهندسة صناعية وإنتاج
schoolبكالوريوس
event_available2026-07-15
السؤال
Transcribed Image Text:
Question 4: (7 marks)
A servicing equipment used in SERVISCO company is
composed of four subsystems is shown in diagram below.
Knowing that:
The reliability of the subsystem A is 0.75
The reliability of the subsystem B is 0.81
The reliability of the subsystem C is 0.67
The reliability of the subsystem A is 0.98
Subsystem A
System C
Sudnystem D
Calculate the reliability of this system.
During testing period, 10 servicing equipment have been
evaluated. The record of breakdowns is presented in the table
below:
Number of 02356
breakdowns
Frequency of 0.10502040.1
occurrence
The average cost of breakdown is 70KD. In order to
improve the reliability, SERVISCO company decides to
contract out the preventive maintenance to MSC company.
The contract will include fixed fees of 100 KD and the cost
of:
-Spare parts: 5KD
.Labor: 50KD
.Consumables: 10KD
-Equipment: 5 KD
MSC company performed a trial period in which 10
servicing equipment have been controlled, the record of
breakdown presented by this company is shown by the
table below:
Number of 0124
breakdowns
Frequency of 0.70.30.10.05
Occurrence
2 If SERVISCO expect a 30 % reduction of total annualized
maintenance cost (AMC), is it better to contract the
preventive maintenance service to MSC?
To sign the contract, SERVISCO require a minimum 50%
reliability improvement. MSC suggests to duplicate only
two subsystems which represent the lower reliability. Only
one similar redundant component will be considered for
each subsystem. Will SERVISCO sign the contract with
MSC? If yes, calculate the annualised maintenance cost.
check_circle الجواب — حل مفصل خطوة بخطوة
hourglass_top
🔒
الحل الكامل متاح للمشتركين
اشترك في أرشيف الأسئلة لعرض هذا الحل وآلاف الحلول المفصلة خطوة بخطوة من معلمين معتمدين.