السؤال

Transcribed Image Text:

Use the following to answer the next five questions (questions 1-5): Using the information below, develop a material requirements plan for end item A and components B, C, & F. 95 and 40 units of A are needed in weeks 6 and 8, respectively. Item On-Hand A 25 On-Order Lead Time 1 wk Order Size lot-for-lot B 10 20 (wk 2) 1 wk lot-for-lot C(2) 2 wks lot-for-lot B(3) A D 100 1 wk 100 T F 2 wks 200 F D F(2) The planned-order release(s) for Item F is (are): Week 1: 400, Week 2: 200, Week 3: 200 Week 1: 400, Week 2: 200 Week 1: 200, Week 2: 200, Week 3: 200, Week 4: 200 Week 1: 200, Week 3: 200 Week 3: 400, Week 5: 200