The Global Tea and Organic Juice companies have merged. The following information has been collected
for the "Consolidation Project".
Activity
Description
Predecessor
Optimistic
Most likely
Pessimistic
(a)
(m)
(b)
-23456780272217
Codify codes
None
16
19
28
File articles of unification
None
30
30
30
Unify price and credit policy
None
60
72
90
Unify personnel policies
None
18
27
30
Unify data processing
1
17
29
47
Train accounting staff
1
4
7
10
Pilot run data processing
5
12
15
18
Calculate P & L and balance sheet
6,7
6
12
24
9
Transfer real property
2
18
27
30
Train salesforce
3
20
35
50
11
Negotiate with unions
4
40
55
100
Determine capital needs
8
11
20
29
Explain personnel policies
11
14
23
26
end
Secure line of credit
1. Compute the expected time for each activity.
9, 12
13
16
19
10, 13, 14
0
0
0
2. Compute the variance for each activity.
3. Compute the expected project duration.
4. What is the probability of completing the project by day 117?
5. What is the probability of completing the project by day 110?
6. What is the probability of completing "Negotiate with unions" by day 95?