السؤال

Transcribed Image Text:

Using the priority list T6, T4. T7. T1, T2, T3, T5, schedule the project below with two processors. Due Sat 03/28/2020 11t T1 (2) T4 (7) T6 (4) T2 (5) T5 (3) T7 (9) T3 (12) End a List the task numbers of the tasks processor one works on, in order. For example, if they work on T1 then T4 then T7, enter: 1,4,7. Ignore idle time. TIP Enter your answer as a list of integer or decimal numbers separated with commas: Examples: -4, 3, 2.5172 Enter DNE for Does Not Exist, oo for Infinity Get Help: VIDEO VIDEO +