السؤال
Transcribed Image Text:
Assigned Work:
A certain project is defined by the data given in the following table:
Predecessor Duration
Activity
Workers
(Weeks)
A
6
5
B
3
4
C
A
9
3
Ꭰ
B
5
2
E
B
4
5
F
D
2
4
G
E
8
6
a) Create a plan for this project in MSP following our usual conventions and use MSP's
Project Summary Task feature to compute the overall project duration. Inspect the resulting
project network and make sure there are no dangling ends. Assign the required workers to
each project activity, assuming that each activity starts as soon as possible. Make sure the
view in MSP shows the resulting resource loading graph, then save your project plan under
the file name 'HW8a".
(50 points)
b) For the project plan you generated in part (a), rearrange the timing of individual activities
within MSP to reduce the overall fluctuation in resource demand. Assume that the project
duration cannot be extended and remember that the precedence relationships must not be
violated. Save your revised project plan under the file name 'HW8b.
(25 points)
c) If there are only 10 workers available for this project, rearrange the timing of individual
activities within MSP to ensure that the project can be completed as quickly as possible but
without violating the resource limit. In this case, the project duration may be extended if
necessary (but making sure to maintain all precedence relationships). Save your revised
project plan under the file name 'HW8c'.
(25 points)