السؤال
Transcribed Image Text:
Chapter 8 Scheduling Resources and Costs 283
You have prepared the following schedule for a project in which the key resource
is a tractor(s). There are three tractors available to the project. Activities A and D
require one tractor to complete while activities B, C, E, and F require 2 tractors.
Develop a resource-constrained schedule in the loading chart that follows. Use
the parallel method and heuristics given. Be sure to update each period as the com-
puter would do. Record the early start (ES), late finish (LF), and slack (SL) for the
new schedule.
4
C
8
2
2
2
10 A
4
6
4
10
Legend
11
1
ES ID EF
14 5
5
D
10
10 F 12
SL
SL
0 1
0
020
LS DURALF
5
0 B
5
5
10
10 2 12
Resource
0 2 0
05 5
5
E
8
2
2
2
7 3
10
Use the following heuristics:
Minimum slack
Smallest duration
Lowest identification number
ID RES DUR ES
LF SL O
1
2
3
4
5
6
7
8
9
10
A 1 4
B2
10
5
C2 4
D1
E2
5
3
F 2 2
11 12 13
14
15
15
Resources available
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
Resources scheduled
"The solution to this exercise can be found in Appendix 1.