تم الحل ✓
categoryهندسة صناعية وإنتاج
schoolبكالوريوس
event_available2026-07-15
السؤال
Transcribed Image Text:
A shop works a 400-minute day. The manager of the shop
wants an output rate of 200 units per day for the assembly
line that has the tasks shown in the following table. Do the
following:
a. Construct the precedence network and calculate the
cycle time.
b. Assign tasks according to "Assign the task with the
most followers" rule. In the case of a tie, use "Assign
the task with the longest time" heuristic rule.
c. Calculate the balance delay.
Immediately
Immediately
Precedes
Task
Precedes
Task
Task
Task(s)
Time
Task
Task(s)
Time
a
b, c, d
0.5
g
h
0.4
e
1.4
k
0.3
C
e
1.2
i
j
0.5
d
f
0.7
j
k
0.8
e
g, j
0.5
k
f
i
1.0
m
E I
0.9
0.3