12-26. For the network below with all times indicating weeks, answer the following questions and
justify your answers:
a. What is the impact on the end date of the project if activity I slips by three weeks?
b. By how many weeks can activity D slip before the project end date gets extended?
c. If activity A slips by one week, how will the slack in activity G be impacted?
d. If activity H can somehow be compressed from seven weeks to two weeks, perhaps by
adding a significant number of resources, what will be the impact, if any, on the end date of
the project?
A, 5
D, 8
G, 5
J, 3
Start
B, 4
E, 5
H, 7
End
K, 7
C, 8
F,6
I, 3