Consider the following project network. The numbers (in days) on the arcs represent the
set (a,m,b). Start node is 1 and end node is 6. Write down the mean and variance of the
activity times on top of the arcs using the network below. Identify the critical path and then
compute the mean and variance of the project completion time. If a customer wants the
project completed in 42 days, what is the probability of that happening? What completion
time should be offered to the customer to be 99% sure of being done by then?
(0, 3, 12)
(2,5,8)
(1, 7, 13)
(4,16,28)
5
6
(2, 2, 2)
(3,3,9)