3. (20%) Develop a resource schedule in the loading chart that follows. Use the parallel
method and heuristics given. Be sure to update each period as the computer would do.
Note: activities 2, 3, 5, and 6 use two of the resource skills. Three of the resource skills
are available. How has slack changed for each activity? Has the risk of being late
changed? How?
0 11
2 1 2
13 5
3 2 3
4 4 8
2 1 3
3 4 8
010
0 2 3
3 5 8
0
20
3
3 3
3
56
2
2 2
5
3
00
8
Use the following heuristics:
Minimum slack
Smallest duration
Lowest identification number
ID RES DUR ES LF SLO
1
2
2 3 0 3
3
4
5
60
2122
4 1
00
8
5
3
8
2 3
2 2
8 6 10
020
8 2 10
Legend
ES ID EF
SL RES SL
LS DUR LF
List the order in which your
activities are scheduled
1
2
3
4
56
7
8
9
10
11 12 13
Resources scheduled
Resources available
3
3
3
3
3
3
3
3
3
3
3
3
3
What is the schedule slack for 1
,3
and 4
?
Which activities are critical now?